Milling and paving work continues

On Tuesday through Friday, APAC Shears of Salina will continue work on the City of Salina’s annual asphalt mill and inlay project. The schedule is as follows, weather permitting.

Milling
Ninth Street from Walnut to Ash, Wednesday-Friday

Paving
Fifth Street from Pacific to Harsh, Tuesday

Woodland from Fifth Street to Second Street, Wednesday

Beverly from Rocket to Steahlin, Wednesday

Duval from Crawford to Haven, Thursday

Quincy from Belmont to Kensington, Thursday and Friday

The work consists of milling the existing asphalt street surface 1.5 inches and replacing it with new asphalt to rehabilitate and preserve the pavement section. Permanent pavement markings will be placed shortly after the resurfacing.

The work will be completed with lane closures. Residents and business owners will be notified prior to changes in access to properties. On-street parking in work zones will be prohibited. Any vehicles or equipment left on the street on the day paving is scheduled may be towed at the owner’s expense.

The $1.5 million project is a major component of the City of Salina’s $4.7 million 2018 maintenance capital improvement program.