2015 Mill and Inlay Road Work Update

CityofSalinaThe City’s annual Mill and Inlay work will continue on Monday September 28, 2015. The schedule for September 28 – October 1, weather permitting, is as follows:

September 28: Planet Avenue – Sullivan Drive to 800 feet north of Sullivan Drive
                             Debold Avenue – 9th Street to Market Place
                             Front Street – Crawford Street to Prescott Road

September 29: Planet Avenue – Sullivan Drive to 800 feet north of Sullivan Drive
                             Jerry Ivey Park – Parking lots

September 30: Debold Avenue – 9th Street to Market Place

October 1: Jerry Ivey Park – Parking lots

While the work is in progress, individual roads will be closed to through traffic. The contractor will begin setting traffic control at 7 a.m. Residences and businesses will be notified prior to changes in access to properties. On-street parking in work zones will be prohibited. Any vehicles, or equipment, left on the street on the day paving is scheduled may be towed at the owners’ expense.

This project is a major component of the 2015 Street Maintenance Program. The project consists of milling the existing asphalt street surface 1.5” deep and then resurfacing it with new asphalt to rehabilitate and preserve the pavement section. Permanent pavement markings will be placed shortly after resurfacing is complete.

For additional questions, contact the Department of Public Works at 785-309-5275.