On Monday, May 22 through Friday, May 26, Vance Brothers Construction Company will perform the annual micro-surfacing maintenance on the following streets for the City of Salina, weather permitting:
|
Mon, May 22 |
Front; Iron to Ash |
|
Stack; Delaware to Missouri |
|
|
Montrose; Crawford to South |
|
|
Deborah; west of Skyline to Eastmoor |
|
|
Melrose; Knollcrest to west of Fairdale |
|
|
Skyline |
|
|
Tues, May 23 |
Edgehill |
|
Fredrich |
|
|
McAdams east of Moundview |
|
|
Wed, May 24 |
Knollcrest |
|
Kaci Court |
|
|
Kaci Circle |
|
|
Moundview; Faith to Crawford |
|
|
Thurs, May 25 |
Golfview |
|
Manchester; Republic to McAdams |
|
|
Meadowbrook |
|
|
Fri, May 26 |
Front; Ash to Elm |
|
Otis; 9th to Santa Fe and 4th to 3rd |
|
|
Wayne; Lewis to Belmont and Huntington to Redhawk |
Roads will be closed to traffic during construction for a period not to exceed 8 a.m. to 5 p.m. Residents will be provided sufficient notice of closures and special requests will be accommodated.